Cineworld

Services

Soft Strip Out
Internal Demolition

53,000

sq. ft

2 Weeks

Duration

Wolverhampton

Location

Jack Kennedy

Site Manager

Project Summary

Strip out of multiple theatres and foyer at multiplex cinema

Schedule of Work

Strip out foyer including ticket counters & concession store
Remove theatre seating
Strip out WC's and sanitary ware
Remove floor finishes & wall finishes
Strip out suspended ceilings and grid
Demolish partition walls and glazed curtain walling & doors
Remove spiral staircases
Remove and recycle all debris & waste materials