top of page

SCS

Services

Soft Strip Out
M&E Strip Out

11,730

Sq ft.

5 Days

Duration

Solihull

Location

Jack Kennedy

Site Manager

Project Summary

Strip out of a large furniture store on a retail park.

Schedule of Work

Strip out carpet, vinyl & laminate floor coverings
Remove suspended ceiling, timber grid ceiling & high-level open grid ceiling
Strip out perimeter skirting, decorative wall panelling & column claddings
Remove partitions & screens
Strip out M&E including lighting & electrical services

Map of case studies (click to see links)

Umberslade_SnagZero_TM WHT.png

Minimum fuss. Maximum service.

We’re dedicated to mimimising fuss and maximising our level of service.

SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.

bottom of page