Genesis House
Services
Principal contractor
Soft strip out
M&E strip out
Internal demolition
18,000
Sq. m
10 Weeks
Duration
Milton Keynes
Location
Gabe Pettitt
Snr. Site Manager
Project Summary
Strip out of 4 floor office for change of use, in the heart of Milton Keynes
Schedule of Work
Floor coverings from raised access floor, ceilings & lighting
Lightweight partitions
Fire barriers, doors & frames, skirting, riser fronts
Tea points
M & E to include, fan coil system, a/c, ductwork, grilles and all associated pipework, strip out risers, all lighting, power and data, fire alarm, comms equipment, floor boxes.
WCs: Full strip out to shell of all floor coverings, wall finishes, ceiling finishes, cubicles, IPS systems, vanity units and all sanitary ware.
Roof: Strip out redundant roof plant, cradle systems and supporting steelwork
Roof: Strip out of roof internal plant room
Roof: Removal of 2 x external chiller units
Map of case studies (click to see links)
Minimum fuss. Maximum service.
We’re dedicated to mimimising fuss and maximising our level of service.
SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.