top of page

Genesis House

Services

Principal contractor
Soft strip out
M&E strip out
Internal demolition

18,000

Sq. m

10 Weeks

Duration

Milton Keynes

Location

Gabe Pettitt

Snr. Site Manager

Project Summary

Strip out of 4 floor office for change of use, in the heart of Milton Keynes

Schedule of Work

Floor coverings from raised access floor, ceilings & lighting
Lightweight partitions
Fire barriers, doors & frames, skirting, riser fronts
Tea points
M & E to include, fan coil system, a/c, ductwork, grilles and all associated pipework, strip out risers, all lighting, power and data, fire alarm, comms equipment, floor boxes.
WCs: Full strip out to shell of all floor coverings, wall finishes, ceiling finishes, cubicles, IPS systems, vanity units and all sanitary ware.
Roof: Strip out redundant roof plant, cradle systems and supporting steelwork
Roof: Strip out of roof internal plant room
Roof: Removal of 2 x external chiller units

Map of case studies (click to see links)

Umberslade_SnagZero_TM WHT.png

Minimum fuss. Maximum service.

We’re dedicated to mimimising fuss and maximising our level of service.

SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.

bottom of page