top of page

Robins & Day Citroen

Services

Soft Strip Out

2,000

sq. ft

1 Week

Duration

London

Location

Jack Morton

Contracts Manager

Project Summary

Strip out of Robins & Day Citroen/Peugeot dealership, including showroom, sales offices and staff areas.

Schedule of Work

Strip out counter units and fixtures & fittings
Demolish partition walls & glazed partitions
Remove carpets, barrier matting & vinyl floor surfaces
Remove ceramic & timber skirting
Strip out suspended ceiling tiles
Strip out canteen & WCs
Remove external signage

Map of case studies (click to see links)

Umberslade_SnagZero_TM WHT.png

Minimum fuss. Maximum service.

We’re dedicated to mimimising fuss and maximising our level of service.

SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.

bottom of page