top of page

India House

Services

Strip Out
M&E Strip Out

20,000

sq. ft

3.5 weeks

Duration

London

Location

Jack Morton

Contracts Manager

Project Summary

Strip out of 5th floor offices & comms room in SE1

Schedule of Work

Strip out stud wall & glazed partitions & doors
Remove suspended ceilings & carpeted floor finish
Strip out plasterboard ceilings and column casings
Strip out comms room, kitchenette, WCs, radiators & shower
Strip out raised floor cut outs & below floor data cables

Map of case studies (click to see links)

Umberslade_SnagZero_TM WHT.png

Minimum fuss. Maximum service.

We’re dedicated to mimimising fuss and maximising our level of service.

SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.

bottom of page