top of page
Radcliffe Conference Centre
Services
Soft Strip Out
Internal Demolition
£40,000
sq. ft
5 Weeks
Duration
Coventry
Location
Lee Coates
Contracts Manager
Project Summary
Strip out & internal demolition of 75 hotel rooms and reception area at University conference centre ready for major refurbishment
Schedule of Work
Remove furniture, fixtures & fittings
Strip out floor finishes & suspended ceilings
Disconnect & Strip out WC's & sanitaryware, remove wall finishes
Strip out reception area desk, partition walls and glazing
Remove and recycle all debris & waste materials
Map of case studies (click to see links)
Minimum fuss. Maximum service.
We’re dedicated to mimimising fuss and maximising our level of service.
SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.
bottom of page