Project Summary

Strip out & internal demolition of 75 hotel rooms and reception area at University conference centre ready for major refurbishment

Schedule of Work

Remove furniture, fixtures & fittings
Strip out floor finishes & suspended ceilings
Disconnect & Strip out WC's & sanitaryware, remove wall finishes
Strip out reception area desk, partition walls and glazing
Remove and recycle all debris & waste materials