top of page
Friars House
Services
Soft Strip Out
M&E Strip Out
5,000
sq. ft
2 Weeks
Duration
Coventry
Location
Roman Gujda
Site Manager
Project Summary
Soft strip out of University administration office; 7th floor of city centre building
Schedule of Work
Strip out floor finishes, raised floors & suspended ceilings
Demolish non-load bearing walls & remove partitions
Dismantle & remove HVAC systems & ducting, electrical services & data services
Remove and recycle all debris & waste materials
Map of case studies (click to see links)
Minimum fuss. Maximum service.
We’re dedicated to mimimising fuss and maximising our level of service.
SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.
bottom of page