The Fort Retail Park
Services
Soft Strip Out
Internal Demolition
28,000
sq. ft
3 Weeks
Duration
Birmingham
Location
Gabe Pettitt
Snr. Site Manager
Project Summary
Strip out of three adjacent retail units at major retail park
Schedule of Work
Demolish dividing walls between units
Strip out offices and staff room
Strip out stock rooms and remove racking
Remove ceiling systems and floor coverings
Demolish changing areas
Remove and recycle all debris & waste materials