top of page

The Birmingham Rep

Services

Soft Strip Out
Internal Demolition
M&E Strip Out

25,000

sq. ft

5 Weeks

Duration

Birmingham

Location

Roman Gujda

Site Manager

Project Summary

Strip out of this prestigious theatre's lobby and bar area

Schedule of Work

Dismantle & remove glazed entrance lobby & box office counter
Strip out kitchen area plus section of wall & risers, plus waiter station
Strip out bar area including associated services and counter top
Remove circular seating, ceilings, floor finishes and partitions
Strip out WC sanitaryware and cubicles
Cut back & remove cills & steps, form single door openings

Map of case studies (click to see links)

Umberslade_SnagZero_TM WHT.png

Minimum fuss. Maximum service.

We’re dedicated to mimimising fuss and maximising our level of service.

SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.

bottom of page