Brindley Place

Services

Soft Strip Out

6,000

sq. ft

5 Weeks

Duration

Birmingham

Location

Dean Marshall

Site Manager

Project Summary

Strip out of 5 floors of offices in the heart of Birmingham

Schedule of Work

Deconstruction of plasterboard partition walls & glazed partitions
Removal of bulheads
Strip out of acoustic insulation slabs

Map of case studies (click to see links)

Umberslade_SnagZero_TM WHT.png

Minimum fuss. Maximum service.

We’re dedicated to mimimising fuss and maximising our level of service.

SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.