Princess Royal Hospital

Services

Groundworks

£350,000

Approx. Value

14 Weeks

Duration

Telford

Location

Scott Bradley

Site Manager

Project Summary

Foundation work and installation & alteration of services for new and existing buildings.

Schedule of Work

Reduce level dig in internal courtyard, arisings tip off site
Cast new foundation with steel frame
Internal floor slabs for ground floor & first floor
Bases for external AHU’s, ground and roof level
Alterations to external drainage
Drainage work for new buildings