top of page

Dosthill Primary Academy

Services

Groundworks

£350,000

Approx. Value

25 Weeks

Duration

Tamworth

Location

Tom Hewitt

Site Manager

Project Summary

Drainage, concreting work & hard landscaping at Primary School in Tamworth.

Schedule of Work

Drainage works including installation of a Foul Pumping Station (depth 4.5m) and a Storm Pumping Station (3.1m)
Tarmac footpath to new build and regrade/topsoil
Extend playground area
Topsoiling to existing school field
Construct concrete upstand wall to perimeter
Removal of timber haul road

!
Widget Didn’t Load
Check your internet and refresh this page.
If that doesn’t work, contact us.

Map of case studies (click to see links)

Umberslade_SnagZero_TM WHT.png

Minimum fuss. Maximum service.

We’re dedicated to mimimising fuss and maximising our level of service.

SnagZero embodies our commitment to minimise risk, error & complication and maximise expertise, efficiency & safety to reliably deliver a high-quality project.

bottom of page