Benson Community School
Services
Groundworks
£200,000
Approx. Value
18 Weeks
Duration
Birmingham
Location
February 2019
Completion Date
Project Summary
Groundworks to enable construction of new extension.
Schedule of Work
Installed foundations: Piled Footings
Installed Ground Ring Beams
Beam & Block Floors